House Amendment 1 to Senate Bill 60
153rd General Assembly (Present)
Bill Progress
PWB 6/18/25
Amendment is attached to the legislation and awaits consideration
Bill Details
6/18/25
This amendment clarifies that storm response and restoration costs above the costs set forth in the Infrastructure, Safety, and Reliability Plan filed by the electric distribution company with the Public Service Commission for the year the costs are incurred may be recoverable as costs incurred under emergency or extraordinary circumstances.